The Version Velocity Gadget calculates the velocity of a project for a specific version, i.e. the total amount of effort relative to the number of story points for completed work. Specifically, the velocity for a version = (sum of time spent on issues in version + sum of remaining estimated time in version) / (sum of story points realised in version). This metric allows the project managers to plan their next cycle.

Note that a lower velocity is better, as it indicates fewer time was needed to accomplish the amount of work.


Configuration

The velocity is the result of: